Project
Project Logs
This is my log project that focused on Substation Automation System Project for Commissioning and Troubleshooting. The last project that I have been working on is Upgrading Siemens Substation Automation System in Paiton Unit 3, East Java. See my project gallery
Time | Project Name | Location | Scope of Work | Customer |
---|---|---|---|---|
July 2017 – August 2017 | Terminal 3 Soekarno Hatta Airport | Tangerang | Support Substation Automation Engineer for the witness of site acceptance test with Customer Associated with PT. PAS Jaya Mandiri & PT. Siemens Indonesia | PT. Angkasa Pura |
July 2017 – Oct 2017 | GIS 150kV BOGOR BARU | Bogor, West Java | Team Support Substation Automation Engineer Associated with PT. PAS Jaya Mandiri & PT. Siemens Indonesia | PT. PLN (Persero) |
Sep 2017 – Feb 2018 | GITET 275kV Wotu | Wotu, South Sulawesi | Team Support Substation Automation Engineer, Supporting Agus Riyanto (Engineer) Associated with PT. PAS Jaya Mandiri & PT. Siemens Indonesia | PT. PLN (Persero) |
Feb 2018 – Apr 2018 | Factory Acceptance Test | FAT Siemens EM DG SYS Quality Control Lab. Jakarta | Factory Acceptance Test Support Associated with PT. PAS Jaya Mandiri & PT. Siemens Indonesia | PT. PLN (Persero) |
Apr 2018 – May 2018 | GI 150kV Muara Dua | Muara Dua, South Sumatra | Commissioning Siemens Substation Automation System with PLN Pusertif Associated with PT. PAS Jaya Mandiri & PT. Siemens Indonesia | PT. PLN (Persero) |
May 2018 – Jul 2018 | GIS 150kV Summarecon | Summarecon, Bekasi | Commissioning Siemens Substation Automation System with PLN Pusertif Associated with PT. PAS Jaya Mandiri & PT. Siemens Indonesia | PT. PLN (Persero) |
Jul 2018 – Aug 2018 | GI 150kV Martapura | Martapura, South Sumatra | Commissioning Siemens Substation Automation System with Pusertif. Prepare Energize bay Line to Muara Dua Associated with PT. PAS Jaya Mandiri & PT. Siemens Indonesia | PT. PLN (Persero) |
Sep 2018 – Sep 2018 | GI 150kV Tanjung Selor | Tanjung Selor, North Kalimantan | Training PLN Operator GI Tanjung Selor Associated with PT. PAS Jaya Mandiri & PT. Siemens Indonesia | PT. PLN (Persero) |
Sep 2018 – Oct 2018 | GI 66kV PLTMG Bima | Bima, West Nusa Tenggara | Commissioning Siemens Substation Automation System with PLN Pusertif Associated with PT. PAS Jaya Mandiri & PT. Siemens Indonesia | PT. PLN (Persero) |
Nov 2018 – Nov 2018 | GI 150kV Sumbawa | Sumbawa, West Nusa Tenggara | Together with Agam Fajar Haris, Training Operator PLN GI Sumbawa NTB Associated with PT. PAS Jaya Mandiri & PT. Siemens Indonesia | PT. PLN (Persero) |
Nov 2018 – Nov 2018 | GI 150kV Maumere | Maumere, East Nusa Tenggara | Training Operator PLN GI 150kV Maumere Associated with PT. PAS Jaya Mandiri & PT. Siemens Indonesia | PT. PLN (Persero) |
Nov 2018 – Dec 2018 | GI 150kV PLTMG Bolok | Bolok, Kupang, East Nusa Tenggara | Commissioning Siemens Substation Automation System with PLN Pusertif Associated with PT. PAS Jaya Mandiri & PT. Siemens Indonesia | PT. PLN (Persero) |
Jan 2019 – Apr 2019 | GITET 500kV Deltamas | Deltamas, Bekasi | Commissioning Siemens Substation Automation System with PLN Pusertif Associated with PT. PAS Jaya Mandiri & PT. Siemens Indonesia | PT. PLN (Persero) |
Jun 2019 – Jun 2019 | GI 150kV Surabaya Barat | Krian, Surabaya Barat, East Java | Commissioning uprating Trafo 60MVA with ABB IED integrated to Siemens Substation Automation System with PLN Pusertif Associated with PT. PAS Jaya Mandiri & PT. Siemens Indonesia | PT. PLN (Persero) |
Jul 2019 – Jul 2019 | GI 150kV Klaten | Klaten, Middle of Java | Commissioning uprating Trafo 60MVA with ABB IED integrated to Siemens Substation Automation System with PLN Pusertif Associated with PT. PAS Jaya Mandiri & PT. Siemens Indonesia | PT. PLN (Persero) |
Aug 2019 – Aug 2019 | GI 150kV Pandaan | Pandaan, East Java | Energize Team GI 150kV Pandaan Associated with PT. PAS Jaya Mandiri & PT. Siemens Indonesia | PT. PLN (Persero) |
Sep 2019 – Sep 2019 | PJB Paiton Unit 2 | Paiton, East Java | Integration IED Reyrole MV Switch Gear to Siemens Substation Automation System Associated with PT. PAS Jaya Mandiri & PT. Victory Profindo Automation | PT. PLN PJB Paiton |
Oct 2019 – Oct 2019 | GI 150kV Panakukang | Panakukang, Makassar | Point to Point Preparation test to RCC Makassar Associated with PT. PAS Jaya Mandiri & PT. Siemens Indonesia | PT. PLN (Persero) |
Nov 2019 – Nov 2019 | GIS 150kV Pondok Indah | Pondok Indah, Jakarta | Support integration Siemens IED to ABB Substation Automation System Associated with PT. PAS Jaya Mandiri & PT. Siemens Indonesia | PT. PLN (Persero) |
Nov 2019 – Dec 2019 | GI 150kV Muara Wahau | Muara Wahau, East Kalimantan | Commissioning Siemens Substation Automation System with PLN Pusertif Associated with PT. PAS Jaya Mandiri & PT. Siemens Indonesia | PT. PLN (Persero) |
Jan 2020 – Jan 2020 | GITET 275/150kV Sungai Rumbai | Sungai Rumbai, West Sumatra | Together with FX Heru Triantoro: Sharing knowledge about Siemens Protection & Automation System with PLN UPPJ West Sumatra Associated with PT. Saba Pratama & PT. Siemens Indonesia | PT. PLN (Persero) |
Jan 2020 – Jan 2020 | GI 150kV Palangkaraya | Palangkaraya, Borneo | Closing Pending to integrate IED Reyrole for cubicle panel incoming & outgoing 8 GI 150kV Palangkaraya Associated with PT. Saba Pratama & PT. Siemens Indonesia | PT. PLN (Persero) |
Jan 2020 – Jan 2020 | GI 150kV KIIC Margakarya | Karawang, West Java | Closing Pending item Siemens Substation Automation System with PLN Associated with PT. Saba Pratama & PT. Siemens Indonesia | PT. PLN (Persero) |
Jan 2020 – Jan 2020 | GI 150kV Grati | Grati, East Java | Together with FX Heru Triantoro: Support update OHL to GSUT for Siemens Substation Automation System Associated with PT. Saba Pratama & PT. Siemens Indonesia | PT. PLN (Persero) |
This is my documentation while surveying onsite Paiton Unit 3, East Java (2019). Within this site work, I was also involved with the implementation of the Automatic Generation Control Test between DCS Paiton Unit-3 and Java Control Center. It is part of my journey on a substation automation system project.
After the survey and preparation for the outage, (about 1 year of preparation) The Upgrading Project of the Substation Automation System finally finishes in September 2021. Thank you to everyone who has been involved with great teamwork during the commissioning test.